Canada’s B2Gold Corp reports that its new Fekola gold mine in Mali achieved commercial production on 30 November, one month ahead of the revised schedule and four months ahead of the schedule announced in the Optimised Feasibility Study (OFS).

Ramp up to full-scale production at Fekola remains ahead of schedule with gold production well above budget in each of the ramp-up months, beating original recovery, grade and plant availability estimates in the OFS design. By 30 November this year, the mine had produced around 80 000 ounces of gold, approximately 158 % above budget (31 000 ounces). Gold production from the mine in 2017 is now forecast to be between 100 000 and 110 000 ounces, far surpassing the upper end of the original guidance of 45 000 to 55 000 ounces.

The processing plant at the Fekola gold mine (photo: B2Gold).

B2Gold has declared commercial production at Fekola based on an internal commercial production measure of 30 consecutive days of mill throughput at 65 % or greater of nameplate capacity (607 dry tonnes per hour). During the 30-consecutive-day commercial test, the mill achieved an average throughput of 626 dry tonnes per hour. This included an availability for the mill of 95 % (budget was 70 %) for the test period and a recovery that exceeded 95 % (budget was 91 %).

The Fekola mill started processing ore more than three months ahead of schedule on 25 September 2017, with the first pour achieved on 7 October. In October, the first full month of ramp-up and pre-commercial production, the Fekola mill treated 324 525 tonnes of ore (as against 225 804 tonnes budgeted) at an average grade of 3,40 g/t (2,33 g/t budgeted) with a gold recovery of 95,4 % (90,0 % budgeted), producing a total of 33 946 ounces of gold in the month (surpassing budget of 15 100 ounces).

Based on the life of mine (LoM) plan, B2Gold is projecting production of approximately 400 000 to 410 000 ounces of gold from Fekola in 2018, the first full year of production, with low projected cash operating costs and an AISC of approximatelyUS$354 per ounce and US$609 per ounce, respectively.
The Fekola mine is situated in south-western Mali, on the border between Mali and Senegal, about 210 km south of Kayes and 480 km (by road) from Bamako, Mali’s capital. The project entered B2Gold’s portfolio in 2014 as a result of its acquisition of Papillon Resources.

Contact Modern Mining

Title: Editor
Name: Arthur Tassell
Email: mining@crown.co.za
Phone: +27 11 622-4770
Fax: +27 11 615-6108

Title: Advertising Manager
Name: Bennie Venter
Email: benniev@crown.co.za
Phone: +27 11 622-4770
Fax: +27 11 615-6108

BANNER 9

 
Full Name*
Invalid Input

Company Name*
Invalid Input

Your Email*
Invalid Input

Phone*
Invalid Input

Postal Address 1*
Invalid Input

Postal Address 2*
Invalid Input

Postal Code*
Invalid Input

Street Address 1
Invalid Input

Street Address 2
Invalid Input

Postal Code
Invalid Input

Town / City*
Invalid Input

Country*
Invalid Input

Magazine

Invalid Input

Invalid Input