Modern Mining

WorleyParsons RSA, which has designed more deep mine shafts than any other company in the world, has recently completed the first and most critical phase of Wesizwe’s R10,7 billion Bakubung Platinum Mine project near Rustenburg, with the commissioning of the main and service shafts. In addition, the commissioning of the ore-handling system marks a major milestone in the project’s timeline.

“The most important phase in developing a deep underground mine with vertical shafts is equipping and commissioning the shafts to hoist – and we have successfully achieved that within the required timeframe,” says Ryan Illingworth, WorleyParsons RSA’s Project Director for the Bakubung project.

        Headgear of Bakubung’s production shaft.

He adds that with shaft steelwork, rock skips and man cages installed, and the production and service shaft complete, the vital work has been done and the second phase of developing underground infrastructure can continue.

The downcast production shaft, to be used for man and materials, has a hoisting capacity of 250 000 tonnes of ore and 15 000 tonnes of waste per month. A refrigeration system will provide bulk air cooling at a later stage. The layout of the 8,5-m diameter lined production shaft accommodates two 20-tonne skips, a two-deck cage with 12-tonne/150-man payload, a counterweight and a 20-man service cage.

The 7,5-m diameter lined service shaft currently consists of a stage winder and kibble winder originally utilised for the sinking of this shaft but now being used for auxiliary hoisting of rock and materials.

Other major milestones that WorleyParsons has achieved on this project include the construction of the main shaft terrace, main stores, workshops, temporary offices, sewage treatment plant, main access road and the production shaft headgear.

The 83-m tall headgear for the production shaft – for which WorleyParsons RSA received a South African Institute of Steel Construction Award in 2014 in the mining and industrial category – was erected in just 18 days and will be used to service all the conveyances. The three winders are ground-mounted and include a Koepe winder for rock hoisting and a double drum cage/counterweight winder for men and material hoisting.

A significant optimisation effort that WorleyParsons RSA achieved during the first phase of the project was the local development and implementation of a cost-effective and highly efficient roping-up system instead of importing a more expensive system.

Illingworth explains that by working in conjunction with the Tech Edge group, WorleyParsons developed the first locally built Koepe roping-up equipment, suitable for four ropes simultaneously. This tailor-made equipment included deflection sheaves, compression beam, rope reelers and a friction winch, all controlled from a central desk supplied by Schneider. This was specifically designed for Bakubung and is expected to deliver significant savings in both time and cost to the client over the life time of the shaft.

Wesizwe officially launched the Bakubung Platinum Mine development project (previously the Frischgewaagd-Ledig project) on 4 July 2011 and WorleyParsons RSA has been involved in the project for almost a decade, from pre-feasibility and feasibility stages to being appointed as EPCM contractor in 2012.

The mine is located in North West Province on the Western Limb of the Bushveld Complex and is expected to have a lifespan of 35 years and employ over 3 100 people when full production is reached. It will produce 255 000 tonnes per month on steady state for 24 years. Four mining levels are planned ranging from 690 m to 810 m below collar. Both the Merensky and the UG2 reefs will be mined. Merensky reef around the shaft area is intersected at about 730,9 m below collar and UG2 reef is 769,4 m below collar. A concentrator plant will also be built on the mine.

Contact Modern Mining

Title: Editor
Name: Arthur Tassell
Email: mining@crown.co.za
Phone: +27 11 622-4770
Fax: +27 11 615-6108

Title: Advertising Manager
Name: Bennie Venter
Email: benniev@crown.co.za
Phone: +27 11 622-4770
Fax: +27 11 615-6108

BANNER 9

 
Full Name*
Invalid Input

Company Name*
Invalid Input

Your Email*
Invalid Input

Phone*
Invalid Input

Postal Address 1*
Invalid Input

Postal Address 2*
Invalid Input

Postal Code*
Invalid Input

Street Address 1
Invalid Input

Street Address 2
Invalid Input

Postal Code
Invalid Input

Town / City*
Invalid Input

Country*
Invalid Input

Magazine

Invalid Input

Invalid Input